Wednesday, March 30, 2011

House Update 30/03, should have key's by 06/04

A bit going on but here's an update.

Yes the painting was finished on 17/03 . On 18/03 the electrician finished off all the power outlets , light switches, down lights and the flood light at the back.

The plumber also finished off all the tapware throughout the house.

The roller doors are on.

The ceramic tiles into dining, kitchen , living and hallway's were laid on Monday 21/03, grouted Tuesday 22/3.

Carpet laying to bedrooms, media and lounge started Thursday 24/03 , finished Monday 28/03.

Tuesday 29/03 , driveway and alfresco has been formed. Pour is expected to take place on 01/04. Weather permitting. Turf scheduled to be laid Monday 04/04 , weather permitting , Cleaner is booked in for Wed 06/04, we expect to do handover on the Wednesday afternoon / Thursday morning yipee !


1 comment: