Monday, April 4, 2011
Wednesday, March 30, 2011
House Update 30/03, should have key's by 06/04
A bit going on but here's an update.
Yes the painting was finished on 17/03 . On 18/03 the electrician finished off all the power outlets , light switches, down lights and the flood light at the back.
The plumber also finished off all the tapware throughout the house.
The roller doors are on.
The ceramic tiles into dining, kitchen , living and hallway's were laid on Monday 21/03, grouted Tuesday 22/3.
Carpet laying to bedrooms, media and lounge started Thursday 24/03 , finished Monday 28/03.
Tuesday 29/03 , driveway and alfresco has been formed. Pour is expected to take place on 01/04. Weather permitting. Turf scheduled to be laid Monday 04/04 , weather permitting , Cleaner is booked in for Wed 06/04, we expect to do handover on the Wednesday afternoon / Thursday morning yipee !
Yes the painting was finished on 17/03 . On 18/03 the electrician finished off all the power outlets , light switches, down lights and the flood light at the back.
The plumber also finished off all the tapware throughout the house.
The roller doors are on.
The ceramic tiles into dining, kitchen , living and hallway's were laid on Monday 21/03, grouted Tuesday 22/3.
Carpet laying to bedrooms, media and lounge started Thursday 24/03 , finished Monday 28/03.
Tuesday 29/03 , driveway and alfresco has been formed. Pour is expected to take place on 01/04. Weather permitting. Turf scheduled to be laid Monday 04/04 , weather permitting , Cleaner is booked in for Wed 06/04, we expect to do handover on the Wednesday afternoon / Thursday morning yipee !
Monday, March 14, 2011
Thursday, March 3, 2011
03/03 - Tiling has started in Bathrooms , Laundry & Splashback in Kitchen
Still locked out but we noticed that the splashback has been done in the Kitchen and the tiling has started in the bathrooms & Laundry.
Spoke to the SS today who advised that painting will start Monday -7/03 , followed by electrical/plumbing, then carpet & tiles to living area's while the driveway alfresco & turf goes in.
Seems to be some confusion over our completion date though. SS say's it will be a week later then head office are stating. Will clarify this with Construction tomorrow.
Cheers.
Spoke to the SS today who advised that painting will start Monday -7/03 , followed by electrical/plumbing, then carpet & tiles to living area's while the driveway alfresco & turf goes in.
Seems to be some confusion over our completion date though. SS say's it will be a week later then head office are stating. Will clarify this with Construction tomorrow.
Cheers.
Thursday, February 24, 2011
24/02 Kitchen & Bathroom cupboards installed - Pine Frames & Timber Doors Hung
One of the workers must have left a door unlocked today. We took a few shot's had a bit of a look about and locked up on the way out ! Happy Days ! We are quite impressed with the Kitchen much bigger then we were expecting. The high gloss polytec doors look great too. Bi-fold doors into the Media room look great, cavity sliders will create some great sound blocking between the rooms.
Bathroom Cupboard
Kitchen
Kitchen Bench Facing Living Area
Kitchen Facing Window
Ensuite Bathroom Cupboard.
Door & Frame in Master Bedroom.
Tuesday, February 22, 2011
Cornice Work Finished 18/02, External Doors Hung 21-22/02.
The cornice work took a few days last week. Drove past today and the external doors have been hung. For now we have been locked out. Looked inside and the cavity doors , media room bifolds and wardrobe doors have begun too. I even noticed the steel laundry tub sitting in the lounge room. Allworth rang today asking for progress payment number 3 and mentioned that the kitchen would be going in on 24/02, explains why the doors are on. Less then 4 weeks now until we move in ! Yippee.
Tuesday, February 15, 2011
15/02 - Walls & Roof Sheets up - Plaster has been set
Bedroom Robe
Family & Kitchen Walls.
Kitchen
Media Room
Corner of Family Room.
Family Out to Alfresco through Sliding Doors.
14/02, Insulation Installed into walls & roof, gyprock started
Soundcheck insulation in Media room (shot from walk in Robe).
Insulation in Family room.
Insulation in Garage parallel to entry.
Insulation in Main Bedroom.
Sunday, February 13, 2011
Eaves on 09/02 , Electrical, Phone, TV wiring in place 10/02, Gyprock & Insulation Delivered 11/02
The plasterboard , including sound check panels for media room were delivered on 11/02 along with the roof wall & media room insulation. It looks like somebody has started unpacking the insulation (very late on Friday afternoon) I sure hope nobody has knocked any off (get a life if you did !)
Corinthian Sliding Door Frames are in (this shot is the cavity slider from Lounge into Dining/Family).
Eaves are on.
TV, Electrical and Telephone wires are in place throughout the house ready for plaster.
Roof & wall Insulation including Sound proof insulation for Media Room has arrived.
Cornice.
Plasterboard stacked in Family area.