Saturday, January 29, 2011
Thursday, January 20, 2011
Monday, January 17, 2011
Spoke to Supervisor 18/01
I was out at the block today and ran into our Site Supervisor. He told me that the roof tiles are being delivered tomorrow, and they will start work. Bricks will be delivered on Friday. One problem, Trend Windows have only just come back from leave today, so our Windows can't be delivered until 27/01, so the brickie has been put off until the windows get done..... Doh !
Sunday, January 16, 2011
14/01 , Roof Trusses go on, 15/01 - a few adjustments
A few photo's from the Western side (back of the house). The sun was too bright to take shots from the front of the house on my phone. Literally three days to erect wall frames, get the roof on to the fine tuning on day 3. The weather has been fantastic so hopefully this keeps up until the tiles go on through the week. Window frames should also be delivered and go in this week too. Fingers crossed.
Thursday, January 13, 2011
Tuesday, January 11, 2011
We are waiting on our frames......as of 12/01
Slightly over anxious , however we were expecting our Frames to be delivered yesterday.
The Site supervisor had said we would be first cab off the rank on 10/01. I'm sure there is a good reason why....
Will call tomorrow to find out where things are up to .. and post details as soon as I have them. No real rain to speak of and hopefully there won't be any for the rest of the week.
The Site supervisor had said we would be first cab off the rank on 10/01. I'm sure there is a good reason why....
Will call tomorrow to find out where things are up to .. and post details as soon as I have them. No real rain to speak of and hopefully there won't be any for the rest of the week.
Subscribe to:
Posts (Atom)